Please find below very important information about traffic changes and construction on the Tangerine Road Project from the latest traffic alert and project updates.
As a reminder, the Tangerine Road traffic shift from Twin Peaks Road/Dove Mountain Boulevard to Camino de Oeste took place on, Monday, January 16. All traffic in this area was shifted onto the new eastbound lanes of Tangerine Road.
Additionally, I want to remind everyone of the upcoming closure on Camino de Mañana. Tangerine Corridor Constructors (TCC) is scheduled to begin removing and reconstructing Camino de Mañana, south of Tangerine Road. Work activities are scheduled from
February 13 through February 26,
6 a.m. to 4 p.m. each day. During this time you can expect the following:
Camino de Mañana will be temporarily closed from Big Sky Ranch Drive to Tangerine Road
Residents and the traveling public will need to use Twin Peaks Road as an alternate route to access Camino de Manana
Traffic control will remain in place 24 hours a day
Camino de Oeste will remain closed at Camino de Mañana
There may be an increase in noise throughout the area with the increased construction activities
For more information on upcoming work activities, please refer to the summary of work (project update) below and watch for updated traffic alerts
Tangerine Road from Thornydale to La Cholla: Northbound and southbound shoulder work will continue through the entire month of January. Beginning Monday, January 9 crews will be paving temporary detours at various locations on the north and south sides of Tangerine Road in preparation for upcoming utility and drainage work. Once this work begins, the speed limit will be reduced to 25 MPH from Thornydale Road to La Cholla Boulevard
Tangerine Road from La Cholla to La Cañada: Northbound and southbound shoulder work will continue through the entire months of January and February. Beginning Monday, January 9 crews will be paving temporary detours at periodic locations on the north and south sides of Tangerine Road in preparation for upcoming utility work. Once this work begins, the speed limit will be reduced to 25 MPH from La Cholla Boulevard to La Cañada.
Tangerine Road and Twin Peaks / Dove Mountain Intersection: Beginning Thursday, January 12, Tangerine Corridor Constructors will begin work on the southeast corner of the intersection in preparation for paving activities scheduled for Saturday, January 14. Marana Police are scheduled to be onsite throughout paving activities to help direct traffic through the intersection. Once paving is complete, traffic will be shifted to the south side of the intersection. The contractor will continue working on the north side of the intersection through late February when it is scheduled to be complete.
Tangerine Road from Twin Peaks / Dove Mountain to Camino de Oeste: Beginning Tuesday, January 10 through Friday, January 13, the contractor will begin paving the new eastbound lanes of Tangerine Road from Dove Mountain to Camino de Mañana, and half of Camino de Oeste. Traffic control will be shifted during this time and the temporary concrete barriers will be relocated. During paving activities, there will be heavy truck traffic and flaggers on site to help direct the traveling public. Traffic is scheduled to be shifted to the new eastbound lanes by Tuesday, January 17.
Tangerine Road from Camino de Oeste to Thornydale: Beginning mid-February Camino de Mañana will be temporarily closed from Big Sky Ranch Drive to Tangerine Road to allow crews to build the new alignment of Camino de Mañana on the south side of Tangerine Road. During this time, traffic will need to use Twin Peaks as an alternative.
Beginning late February, the contractor will begin paving the new eastbound lanes of Tangerine Road from Camino de Oeste to approximately ¼ mile west of Thornydale Road. Traffic control will be shifted during this time and the temporary concrete barriers will be relocated. During paving activities, there will be heavy truck traffic and flaggers on site to help direct the traveling public. **Please watch for more detailed traffic alerts as we get close to construction dates or visit www.tangerineroad.info **
Schedule January, 2017
North and southbound Twin Peaks/Dove Mountain traffic will be shifted to the west side of the intersection
Southeast corner of Tangerine Road Twin Peaks/Dove Mountain intersection will be paved
Beginning work on final quadrant of Tangerine Road Twin Peaks/Dove Mountain Intersection
Eastbound travel lanes will be paved from Twin Peaks/Dove Mountain to Camino de Oeste
East and westbound traffic will be shifted to new eastbound travel lanes from Twin Peaks/Dove Mountain to Camino de Oeste
Work will begin on new westbound travel lanes and continue through May 2017 (Twin Peaks/Dove Mountain to Thornydale)
Temporary detours will be paved on the north and south side of Tangerine Road from Thornydale to La Cañada
Traffic will be shifted to the detours periodically through mid-February
February 2017
Camino de Mañana will be closed from Big Sky Ranch Drive to Tangerine Road while the new alignment is built
Eastbound travel lanes will be paved from Camino de Oeste to ¼ mile west of Thornydale Road
East and westbound traffic will be shifted to new eastbound travel lanes from Camino de Oeste to ¼ mile west of Thornydale Road
Work will begin on the new westbound lanes from Thornydale to La Cholla
Tangerine Corridor Constructors (TCC) Contact Information: For general public relations, please contact Kristi Shepherd at
520.623.3073 or email
[email protected]
If you have any interest in the many services provided at no charge to businesses located in this project, please feel free to contact me.