Thank you for your interest in the Tangerine Road Improvements.
The contractor is working on landscaping and utility adjustments along the east and westbound lanes of Tangerine Road from Thornydale Road to the end of the project, west of the Dove Mountain/Twin Peaks intersection. They are also working along north and southbound Thornydale Road. Work will continue in this area through early February, 2018. Motorists should expect intermittent lane restrictions around the work area. Some restrictions may be in place 24-hours in order to allow concrete to cure prior to traffic being allowed over it.
If you have any additional questions or concerns, please contact Kathy or Nanette at (520) 623-3073 or by email at [email protected]. We look forward to working with you throughout the project, and encourage any feedback to ensure the Project Team can deliver a beneficial project for the whole community.
Please be aware of bicyclists and pedestrians in the area and ensure that dogs, horses and other animals are not in the construction zone to ensure the safety of all.