June 8-15 Tangerine Road Final Paving At La Cholla Intersection Thank you for your interest in the Tangerine Road Improvements.
During the week beginning June 11, the contractor will complete the final paving operations along Tangerine Road from east of the Thornydale Road intersection to just west of La Canada Drive. Work hours will be from 6:30 a.m. to 5 p.m. each weekday. The paving operation is scheduled to be complete by Friday, June 15, 2018.
Tangerine Road will open to two lanes of travel in each direction by 5 p.m.Friday, June 15. The work will include placing the final lift of pavement on La Cholla Boulevard north and south of, and through the intersection of Tangerine Road.
On Monday, June 11 and Tuesday, June 12 from 6:30 a.m. to 5 p.m. each day, the contractor will place the final lift of pavement along north and southbound La Cholla Boulevard, up to the Tangerine Road intersection. Because of the nature of this paving operation, sections of the intersection, will have temporary movement restrictions to vehicular, pedestrian and bicycle traffic.
On Monday, June 11, traffic will be shifted to the northbound lanes (east side of the roadway) while the contractor paves the southbound lanes.
Traffic will be reduced to one lane in each direction.
All turn movements will be permitted.
Flaggers will be on site to direct traffic.
·Motorist will be redirected around the work area.
Access to businesses in the area will be maintained.
Travelers in this area should plan for delays and use alternate routes.
Restricted travel movements through the intersections will end by 5 p.m.
On Tuesday, June 12, traffic will be shifted to the southbound lanes (west side of the roadway) while the contractor paves the northbound lanes.
Traffic will be reduced to one lane in each direction.
All turn movements will be permitted.
Flaggers will be on sight to direct traffic.
Motorists will be redirected around the work area.
Access to businesses in the area will be maintained.
Travelers in this area should plan for delays and use alternate routes.
Restricted travel movements through the intersections will end by 5 p.m.
On June 10 through June 14 the contractor will complete final striping at intersections and along Tangerine Road from Thornydale Road to La Canada Drive.The contractor will work from 8 p.m. to 5 p.m. each night to complete the work. Motorist should watch for lane restrictions around the work area.
Tangerine Road will open to two lanes of travel in each direction by the end of the day Friday, June 15.
In the event of mechanical or weather-related issues, the above schedule of work could change without notice